3406C GENERATOR SET ENGINE Caterpillar


Cylinder Head Assembly

Usage:

Remove & Install Cylinder Head Assembly

Start By:

a. remove rocker shaft assemblies and push rods

b. remove water temperature regulator

c. remove fuel injection lines

d. remove exhaust manifold

e. remove aftercooler housing

FLUID SPILLAGE CONTAINMENT

Care must be taken to ensure that fluids are contained during performance of inspection, maintenance, testing, adjusting and repair of the machine. Be prepared to collect the fluid with suitable containers before opening any compartment or disassembling any component containing fluids. Refer to "Tools And Shop Product Guide", NENG2500, for tools and supplies suitable to collect and contain fluids in Caterpillar machines. Dispose fluids according to local regulations and mandates.

1. Remove bolts (1) that hold plate (2), and remove the plate.

2. Remove bolts (3) and (4) that hold the cylinder head assembly to the cylinder block.

3. Fasten a hoist, and remove the cylinder head assembly. The weight is approximately 135 kg (297 lb).


NOTICE

Do not put the cylinder head assembly down on a flat surface. This can cause damage to the fuel injection valves.


4. Remove the gasket, seals (5) and O-ring seals (6) from the spacer plate.

NOTE: The following steps are for installation of the cylinder head.

NOTE: Be sure a new gasket has been installed between the spacer plate and the cylinder block. See the topic "Remove & Install Spacer Plate".

5. Thoroughly clean the spacer plate and the bottom surface of the cylinder head assembly. Install a new head gasket, new seals (5) and two O-ring seals (6).

6. Fasten a hoist, and put the cylinder head assembly in position on the cylinder block.

7. Put clean engine oil on the threads of the cylinder head bolts. Install the cylinder head bolts and washers. Tighten the bolts in sequence shown.

a. Tighten bolts 1 through 14 in number sequence to a torque of 270 ± 25 N·m (200 ± 18 lb ft).

b. Tighten bolts 1 through 14 in number sequence to a torque of 470 ± 20 N·m (345 ± 15 lb ft).

c. Tighten bolts 1 through 14 in number sequence to a torque of 470 ± 20 N·m (345 ± 15 lb ft) by hand.

d. Install the rocker shaft assemblies and push rods. See the topic, "Install Rocker Shaft Assemblies And Push Rods".

e. Tighten bolts 15 through 26 in number sequence to a torque of 270 ± 25 N·m (200 ± 18 lb ft).

f. Tighten bolts 15 through 26 in number sequence to a torque of 450 ± 20 N·m (330 ± 15 lb ft).

g. Tighten bolts 15 through 26 in number sequence to a torque of 450 ± 20 N·m (330 ± 15 lb ft) by hand.

h. Tighten the (3/8 in) bolts to a torque of 45 ± 7 N·m (33 ± 5 lb ft) after the cylinder head bolts (3/4 in) bolts have been given the final torque.

NOTE: If the studs for the exhaust manifold were removed, install new studs, and tighten them to a torque of 35 ± 5 N·m (26 ± 4 lb ft).

8. Make an adjustment to the valves to have a clearance of 0.38 mm (.015 in) for inlet and 0.76 mm (.030 in) for exhaust. Tighten the locknuts for the valve adjustment screws to a torque of 28 ± 4 N·m (21 ± 3 lb ft).

9. Install the valve cover bases and the inner fuel lines. See the topic "Install Rocker Shaft Assemblies & Push Rods".

10. Install the valve covers. See the topic "Install Valve Covers".

11. Install plate (2).

End By:

a. install aftercooler housing

b. install exhaust manifold

c. install fuel injection lines

d. install water temperature regulator

e. install rocker shaft assemblies and push rods