Before/After | PRODUCT SUPPORT PROGRAM FOR REWORKING THE STICK ON CERTAIN 336D, 336D L, 340D L EXCAVATORS |
|
6502 | PS44199 |
NOTE: | Caterpillar’s obligations under this Service Letter are subject to, and shall not apply in contravention of, the laws, rules, regulations, directives, ordinances, orders, or statutes of the United States, or of any other applicable jurisdiction, without recourse or liability with respect to Caterpillar. |
NOTE: | This Program must be administered either before or after failure. In either case the decision whether to apply the Program is made by the dealer. When reporting the repair, use "PS44199" as the Part Number and "7755" as the Group Number. If administered before failure, use "56" as the Warranty Claim Description Code and "T" as the SIMS Description code. If administered after failure, use "96" as the Warranty Claim Description Code, and "Z" as the SIMS Description Code. |
NOTE: | The information supplied in this service letter may not be valid after the termination date of this program. Do not perform the work outlined in this Service Letter after the termination date without first contacting your Caterpillar product analyst. |
NOTE: | This Revised Service Letter replaces the 25Feb2014 Service Letter. Changes have been made to the Affected Product. |
TERMINATION DATE |
29Feb2016 |
PROBLEM
The existing stick may experience a crack around PT4 boss weld toe area on certain 336D, 336D L, and 340D L Excavators. |
AFFECTED PRODUCT
Model | Identification Number |
336D | JBT00260-04908 |
336D 2 | WDC00101-00302 |
336D 2GC | NBN00101-00141 |
336D 2L | YCF00251-00595, 598-600, 602, 604, 606 |
336D L | MPL00278-00577 |
340D 2L | HHK00131-00358, 360, 362, 364, 366 |
340D L | JTN00130-00585 |
PARTS NEEDED
No parts needed for this program |
ACTION REQUIRED
If stick cracking occurs, refer to REHS3344, Special Instruction, "Procedure for the Repair of Cracks on Reach Sticks for Certain Excavators", for the Rework Procedure. If the butt weld on PT4 boss is beyond height specification during inspection or after welding repair, please follow grinding procedure to remove the surplus height of seam. IMPORTANT: If the stick is weld repaired, please attach pictures of the failed stick including stick serial number, actual operation hours, and the cracking position when submitting the warranty claim. |
SERVICE CLAIM ALLOWANCES
0-36 mo |
||||||
37-48 mo |
NOTE: This is a 8.0-hour job | ||||||
If the rework is to be performed before crack at PT4, 8.0 hours labor can be claimed. An additional 32.0 hours of labor will be allowed if the stick cracked at PT4. |
PARTS DISPOSITION
Handle the parts in accordance with your Warranty Bulletin on warranty parts handling. |
General Grinding Procedure for eliminating the welding surface at high stress concentration area. Refer to RENR8648, Disassembly and Assembly, the removal and installation procedure for the stick group, for 336D and 340D Machines. 1. To facilitate access to the inspection area, place the stick in the extended position. Refer to Image1.1.1. |
Image1.1.1 |
2. Use a weld gauge in order to measure PT4 boss butt weld. Refer to Image1.2.1. |
Image1.2.1 |
3. If the measurement result is beyond 4mm, refer to Step 4 - 5 in order to remove the surplus height of seam. 4. Use a grinder in order to eliminate original both sides of the PT4 boss butt weld until parallel with base metal. Refer to weld seam grinding area in Image1.3.1 and 1.3.2. |
Image1.3.1 |
Image1.3.2 |
Note A: Ensure that the weld surface is smooth. In the case that the surface is too rough, buff grinding will be necessary. Note B: Do NOT damage the base metal when grinding the original weld seam. Note C: Needle peen the repaired area in order to maximize structure life. 5. Use Cat authorized paint for painting the welds. |