Introduction
The following Special Instruction is used to replace the turbine inlet bellows on C175 Engines.
Do not perform any procedures listed in this Special Instruction until you have read and understood the information.
Required Tooling
Tooling | |
Part Number | Description |
Tool As | |
Tool As |
Required Parts
793F, 795F, 797F, and Locomotive Low Altitude Arrangements | ||
Part Number | Description | Quantity |
V Band Clamp | 8 | |
Bellows As | 4 |
Note: All four turbocharger locations utilize the same turbine inlet elbows on low altitude arrangements.
793F and 795F High Altitude Arrangements | ||
Part Number | Description | Quantity |
V Band Clamp | 4 | |
Bellows As | 2 |
Note: Only the two outside turbocharger locations utilize the new turbine inlet bellows. The inner two turbochargers utilize a different
Note: The 797F HAA does not use this bellows assembly.
Removal and Installation Procedure
- Remove V band clamps (1) from the current turbine inlet bellows and discard the clamps.
Show/hide table
Illustration 2 g03545436 (2) 348-9252 Bellows As - Install the 421-4080 Tool As and compress bellows assembly (2).
- Removed the existing bellows assembly.
Show/hide table
Illustration 3 g03545737 Section view of the bellow tool installed
(A) Bellows tool
(B) Bellow ring
(C) Bellow - Install the 452-6804 Tool As onto the new 443-5940 Bellows As. Refer to Illustration 3 for the correct installation of the tool assembly.
- Compress the new bellows enough to allow for installation between the exhaust manifold and turbocharger.
Note: Ensure that the flow arrow on the bellows is pointing in the correct direction of exhaust flow.
- Release and remove the compression tool after bellows is in place.
- Install new 446-1290 V Band Clamps onto the turbine inlet bellows.
Show/hide table
Illustration 4 g03546119 (3) Bellow ring fully seated
(4) Bellow ring not fully seated - Ensure that the new bellows ring is fully seated under the clamp prior to tightening the V band clamp. Refer to Illustration 4.
Note: If the ring is not fully seated, remove the clamp and seat the ring again.
- Tighten the clamp assemblies to
17 ± 2 N·m (150 ± 17 lb in) . Lightly tap around the clamp and retighten to17 ± 2 N·m (150 ± 17 lb in) .