Introduction

It is both important and necessary for a short block or Remanufactured engine to have adequate (needed) lubrication during the first few seconds of its initial (first) start-up. A start-up without this needed lubrication can cause bearing damage.

It is our recommendation to ALWAYS DO THE PRESSURE LUBRICATION PROCEDURE as given in this publication, BEFORE the initial start-up of a reconditioned or rebuilt engine

Pressure Lubrication Procedure

Some type of oil reservoir with a pressure gauge is needed to do the pressure lubrication procedure. In the procedure that follows, a tank assembly from a 1P0540 Flow Checking Tool Group is used for the oil reservoir. If one of these tanks is used in the pressure lubrication procedure, the inside of the tank must be thoroughly cleaned.


NOTICE

NEVER use the same tank assembly for both, the pressure lubrication procedure and the fuel flow checking procedure. It is not possible to get the tank assembly clean enough to do both operations. ANY AMOUNT OF DIRT, DEBRIS, ETC. CAN CAUSE FUEL NOZZLE FAILURE, if the tank is used for fuel flow checking after it has been used for the pressure lubrication procedure.

Other sources of clean oil under pressure, such as a service shop central oil supply, can also be used for pressure lubrication.


1. Refer to the Operation and Maintenance Guide for the engine that is to have the pressure lubrication. Find the amount of oil needed to fill the engine crankcase to the correct oil level. Put 30 percent of this amount of oil in the tank assembly for use in the pressure lubrication procedure.

NOTE: For some engines, 30 percent of the crankcase fill capacity will make it necessary to fill the tank assembly, shown here, more than one time.

2. Use the necessary fittings and hose to connect the tank assembly to a port that connects to the main oil gallery of the cylinder block. Illustrations (A), (B) and (C) are examples of connecting points for some engine models.

For engine model (A), remove a plug at the rear of the right side cylinder head and make the connection as shown.

For engine models (B) and (C), remove plug (1) or (2) on the right side of the cylinder block and connect the pressure lubrication equipment.

------ WARNING! ------

Pressure air can cause personal injury. Air pressure MUST NOT be more than 345 kPa (50 psi) at any time.

-------WARNING!-------

3. Adjust the air pressure regulator to 240 ± 35 kPa (35 ± 5 psi). Connect shop air pressure to the tank assembly to move the oil from the reservoir into the main oil gallery and engine lubrication oil passages within the cylinder block.

NOTE: If shop air pressure is not available, the tank assembly shown has a hand pump that can be used to get the minimum pressure needed.

4. After the pressure lubrication procedure is complete, shut off the air pressure. Disconnect the pressure lubrication equipment. Be sure to install the plug in the hole that was used for pressure lubrication.

5. Add the remainder of oil that is needed to fill the engine crankcase to its correct oil level. REMEMBER that 30 percent of the oil needed to fill the crankcase to its correct level has already been installed during the pressure lubrication procedure.

NOTE: Before the initial engine start-up, turn the crankshaft a few revolutions, with the governor control in the FUEL OFF position, to get some movement of the lubrication oil within the engine.

Caterpillar Information System:

Use of 1U5753 Seal Starter Tool to Install Recoil Bearing Seals{0729, 4151} Use of 1U5753 Seal Starter Tool to Install Recoil Bearing Seals{0729, 4151}
Using the 1U5470 Engine Pressure Group{0781} Using the 1U5470 Engine Pressure Group{0781}
Installation of the Step Buffer Seal Assembly, the U-Cup Seal, and the Double Lip Wiper Seal in Hydraulic Cylinders{7555, 7562} Installation of the Step Buffer Seal Assembly, the U-Cup Seal, and the Double Lip Wiper Seal in Hydraulic Cylinders{7555, 7562}
Using the NEXG4507 3176 Truck Functions ECAP Service Program Module{0781, 0782} Using the NEXG4507 3176 Truck Functions ECAP Service Program Module{0781, 0782}
Using the Caterpillar Fuel Flow Monitor System{0782, 1000, 1250} Using the Caterpillar Fuel Flow Monitor System{0782, 1000, 1250}
Installation of 9Y3499 Fuel Line Clamps Parts Kit{1252} Installation of 9Y3499 Fuel Line Clamps Parts Kit{1252}
Using the 1U7326 Governor Calibration Bench{1264, 0778} Using the 1U7326 Governor Calibration Bench{1264, 0778}
Installing the VR3 Voltage Regulator On SR4 Generators{4467} Installing the VR3 Voltage Regulator On SR4 Generators{4467}
Assembly of Multiple Row Modules on Folded Core Radiators{1353} Assembly of Multiple Row Modules on Folded Core Radiators{1353}
Installation of Service Replacement Woodward Governor Group{1264} Installation of Service Replacement Woodward Governor Group{1264}
Using the 1U6602 Photo-Tach Group{0775} Using the 1U6602 Photo-Tach Group{0775}
Installation and Wear Inspection of Duo-Cone Seals with Formed Steel Seal Rings{7555} Installation and Wear Inspection of Duo-Cone Seals with Formed Steel Seal Rings{7555}
PEEC - Related OEM Truck System Responsibilities and Troubleshooting Guide{0781, 0782} PEEC - Related OEM Truck System Responsibilities and Troubleshooting Guide{0781, 0782}
Governor Performance Data{1264} Governor Performance Data{1264}
Installation of Service Replacement Cylinder Block{1201} Installation of Service Replacement Cylinder Block{1201}
Operating Instructions for Caterpillar 8T7792 Mini Torch{0679} Operating Instructions for Caterpillar 8T7792 Mini Torch{0679}
Operation of 1U8851 and 1U8852 Refrigerant Charging Cylinders{7320} Operation of 1U8851 and 1U8852 Refrigerant Charging Cylinders{7320}
Installation Of 9G6981 And 7T8000 Voltage Converter Assemblies{1421} Installation Of 9G6981 And 7T8000 Voltage Converter Assemblies{1421}
Installation Of Track Groups With Split Master Links{4176} Installation Of Track Groups With Split Master Links{4176}
Use Of 6V-4180 Timing Fixture Group To Check Off-Engine Timing Dimension Setting{1251, 0653} Use Of 6V-4180 Timing Fixture Group To Check Off-Engine Timing Dimension Setting{1251, 0653}
Using the 1U-8860 Large Engine Blowby Pickup Group{0781, 0785} Using the 1U-8860 Large Engine Blowby Pickup Group{0781, 0785}
Using the 1U8660 Boring Bar Hydraulic Unit and Attachments{0672} Using the 1U8660 Boring Bar Hydraulic Unit and Attachments{0672}
Service Replacement Of Stitt Plugs With Champion Plugs On G379, G398, ; G399 With Shielded Altronic Ignition{1555, 1558} Service Replacement Of Stitt Plugs With Champion Plugs On G379, G398, & G399 With Shielded Altronic Ignition{1555, 1558}
Nozzle Assembly Replacement for Type 2 Fuel Injectors{1254} Nozzle Assembly Replacement for Type 2 Fuel Injectors{1254}
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.